As many as 90 workers of Barapukuria Coal Mining Company Limited (BCMCL) have tested positive for Covid-19, prompting the management of the state-owned company to halt production from Friday afternoon.
Among the workers, 50 are Chinese.
Besides, 400 other workers have been asked to remain in home isolation, officials said on Saturday, adding that production would resume after 10 days.
ALSO READ - Barapukuria mine halts operations
Engineer Saiful Islam Sarkar, a manager of the mine, said that coal lifting work from the 1306 phase started on July 26 on a trial basis and till Friday, "we were able to lift 5,000 tonnes of coal".
However, 40,000 tonnes of coal are in stock, which will be used to aid power generation, said Saiful.
Meanwhile, samples of local workers in the 1041 phase have been collected and those testing negative will be allowed to join work, he added.