92% works of entire Padma Bridge project completed: Quader

BSS . Dhaka
04 Apr 2022 00:00:00 | Update: 04 Apr 2022 00:01:31
92% works of entire Padma Bridge project completed: Quader
An aerial view of the under construction Padma Bridge – Shamsul Haque Ripon

Road Transport and Bridges Minister Obaidul Quader on Sudnay said the Padma Bridge would be opened for vehicular movement by June 2022.

He made the announcement while speaking at a review meeting on the progress of the Padma Multiple Bridge Project at the Bridge Division conference room.

Quader, also the Awami League General Secretary, said about 97 per cent work of the main bridge has already been completed, while 90.5 per cent of the river engineering work of the bridge project has been completed and 65.68 per cent of carpeting work of main bridge done.

He said the overall progress of the project is around 92 per cent.

Besides, the road transport and bridges minister said, the gas line installation work has been completed by 99 per cent, while 400 KVA power line installation work by 79 per cent.

Chaired by Bridge Division Secretary Md Monjur Hossain, the meeting was attended, among others, by Cabinet Secretary Khandker Anwarul Islam and project director Md Shafiqul Islam.

×