Home ›› 07 Sep 2021 ›› News

Survey, design completed for 31-km 1st subway metro

BSS . Dhaka
07 Sep 2021 00:00:00 | Update: 07 Sep 2021 02:41:53
Survey, design completed for 31-km 1st subway metro

The government has successfully completed study, survey and basic design for construction of 31.241-km first ever underground and elevated Mass Rapid Transit (MRT) Line-1 between Airport- Kamalapur and Purbachal-Natun Bazar-Pitalganj of Rupganj route.

“With maintaining health guidelines strictly, we’ve also completed 77 per cent work of the detailed design of the project,” Managing Director of Dhaka Mass Transit Company Limited MAN Siddique told BSS on Monday.

He said the joint survey work has been completed for acquisition of 92.9725 acres of land at Rupganj in Narayanganj district.

“The government led by Prime Minister Sheikh Hasina has planned to bring the capital city under a modern transport system so that the city dwellers can avail modern transport facilities,” Siddique added.

According to the project details, the government has taken up MRT Line-1 project for construction of the country’s first ever 31.241-km underground and elevated expressway between Airport-Kamalapur route and Purbachal-Natun Bazar-Pitalganj Depot, Rupganj route.

Under the part one of MRT Line-1, Airport Route from Airport to Kamalapur will have 19.872 km long sub-way with 12 stations. The part two is Purbachal Route (Natun Bazar to Pitalganj Depot, Rupganj) and this route will have 11.369 km elevated way with nine stations, of which seven stations will be overhead and Natun Bazar and Jamuna Future Park stations will be underground as part of the airport route.

The managing director said that the Natun Bazar station will have inter-change facility, from where passengers will have scope to go to Airport route from Purbachal or Purbachal route to Airport using the inter-change.

He said the joint survey has been completed to acquire 92.9625 acres of land for depot and depot access corridor of MRT Line-1 at Pitalganj and Brahmankhali mouzas of Rupganj upazila in Narayanganj district.

The authority has floated expression of interest (EOI) for appointing consultant to oversee construction work in February, 2021.

In July, the evaluation report of Expression of Interest (EOI) and Request for Proposal (RFP) have been sent to Japan International Cooperation Agency (JICA) for its consent.

A tender was invited for the construction of the depot of MRT Line-1 at Pitalganj on June 10 and the deadline for submitting the tender is October 6.

×