Home ›› Power & Energy

RADP: EMRD achieves 103.04% progress

UNB . Dhaka
23 Jul 2023 21:56:02 | Update: 23 Jul 2023 22:37:21
RADP: EMRD achieves 103.04% progress

The Energy and Mineral Resources Division (EMRD) has achieved 103.04 per cent progress in the implementation of its revised annual development programmes (RADP).

Such information on the RADP achievement was shared by the officials at a reviewed meeting of the division on the progress of projects of EMRD from July 22 to June 23 on Sunday.

Appreciating the officials’ remarkable success, State Minister for Power, Energy and Mineral Resources Nasrul Hamid has said schemes should be taken up keeping in mind the future prosperous Bangladesh.

"It's necessary to strengthen team initiative and implement projects quickly. Nobody should suffer from indecisiveness,” he said.

He said EMRD has implemented 100 per cent of ADP for the last two consecutive years and this should be continued.

He directed the distribution companies under EMRD to take the initiative to increase the planned communication activities to build trust-based relationships with their customers.

It was informed in the meeting that in the financial year 2022-23, under the annual development programme, a total of Tk 4053.20 crore was allocated against 44 projects, including 7 GOB and foreign aid projects, 25 own projects and 12 under the Gas Development Fund against which the expenditure was Tk 4176.55 crores.

×